A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the probability that the project takes more than 34 days? 
A) 0.788
B) 0.212
C) 0.945
D) 0.055
Correct Answer:
Verified
Q88: A project's duration can be reduced by:
A)shortening
Q89: Hammock activities allow:
A)project managers to streamline the
Q90: A gentleman farmer maniacally works on academic
Q91: A project has the precedence requirements and
Q92: Summaries for some subsets of the activities
Q94: A gentleman farmer maniacally works on academic
Q95: One approach to reducing project length would
Q96: Which technique would accelerate the completion of
Q97: Activities C,D,and E in the project represented
Q98: A project has the precedence requirements and
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents