Comparative estimates are more accurate than definitive estimates when applied to the same project.
Correct Answer:
Verified
Q21: Estimates based on the assumption that historical
Q22: The order of magnitude cost estimate is
Q24: What learning rate is being demonstrated if
Q28: Rank the four different types of cost
Q29: Effective comparative estimates rely most heavily on:
A)An
Q31: Which of these estimates should be the
Q33: Cost estimates that are based as a
Q34: Once most of the design work is
Q38: An activity with a learning rate of
Q39: If it takes 40 hours to complete