There was no way that the study tour to Italy could cost only $1500 for 14 days and 13 nights and include all transportation,meals and hotels,but the smarmy professor knew that students would balk at a higher advertised price.Once they were thousands of miles away from home in a country where none of them spoke the language it would be easier to tell them about unanticipated charges and approach the more realistic price of $3500 per person.This type of:
A) specification change is a common reason for a cost overrun.
B) lack of definition is a common reason for a cost overrun.
C) low initial estimate is a common reason for a cost overrun.
D) unexpected technical difficulty is a common reason for a cost overrun.
Correct Answer:
Verified
Q18: Provide examples and discuss the differences between
Q73: Activity-based costing and bottom-up budgeting share the
Q74: Whether it is the Boeing V-22 Osprey
Q75: The project plan is supported by:
A)the work
Q76: Poor initial scope development and work breakdown
Q77: A budget that is created by starting
Q79: An advantage of top-down budgeting is:
A)that top
Q80: The new pipe and cable fence would
Q81: What is the project budget for November
Q82: An allocation of extra funds to cover
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents