It was fortunate that the project budget included contingency funding;the top manager had not foreseen that the project would need the services of their elite slide rule squad in more than one area at the same time.Design couldn't complete their work without their services,nor could marketing,or production.Contingency funds came in handy to meet the unanticipated:
A) change in project scope.
B) abnormal project conditions.
C) consequences of Murphy's Law.
D) interaction costs.
Correct Answer:
Verified
Q10: What are four major categories of costs?
Q18: Provide examples and discuss the differences between
Q28: Rank the four different types of cost
Q79: An advantage of top-down budgeting is:
A)that top
Q80: The new pipe and cable fence would
Q81: What is the project budget for November
Q82: An allocation of extra funds to cover
Q85: What is the total project budget in
Q86: What is the total amount budgeted for
Q87: What is the cumulative project budget for
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents