A serious risk factor probably has:
A) a high consequence and a medium likelihood.
B) a high consequence and a low likelihood.
C) a medium consequence and a low likelihood.
D) a low consequence and a medium likelihood.
Correct Answer:
Verified
Q36: The greatest project opportunity occurs when:
A)the project
Q37: The greatest project risk occurs when:
A)the probability
Q38: Project risk is highest during the:
A)termination stage
Q39: The difference between projects that fail and
Q40: The period of highest risk impact for
Q42: A method for conducting risk factor identification
Q43: The probability that funds allocated to the
Q44: A method for conducting risk factor identification
Q45: The probability that project revenues will not
Q46: The construction foreman posted a large sign
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents