As the 80th change order floated across his desk,the project manager wished that he had kept the first 79.What money he had saved in scrap paper might well be lost in charges that could never be recouped from the client."What I need is better:
A) trend monitoring," muttered the manager.
B) configuration control," sighed the manager.
C) specification control," fumed the manager.
D) document control," whimpered the manager.
Correct Answer:
Verified
Q69: Project team members can identify who should
Q70: When work is organized into cost control
Q71: Procedures that monitor emerging project scope against
Q72: A young professor becomes obsessed with the
Q73: The reporting frequency,report recipients,and content required during
Q75: A project management firm that promises to
Q76: Your professor moonlights to make ends meet
Q77: A project manager can identify personnel who
Q78: The step that reflects the formal "go
Q79: All projects are promised in terms of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents