Use the earned value table (all amounts indicated are dollars) to determine the earned value to the nearest hundred dollars given the indicated state of the project. 
A) $7,800
B) $9,600
C) $8,400
D) $6,900
Correct Answer:
Verified
Q72: Use the earned value table to determine
Q73: Use the data to calculate the schedule
Q74: The project baseline is established by combining
Q75: Use the earned value table to determine
Q76: The budget variance is calculated as:
A)earned value
Q78: In earned value management,schedule variance is defined
Q79: Project Terrace has an actual cost of
Q80: Use the earned value table to determine
Q81: The Project Implementation Profile does NOT contain
Q82: Very short work packages would be better