According to CCPM:
A) using a point estimate for activity times is the best approach to project duration estimation.
B) the primary causes of inaccurate duration estimation are behavioral in nature.
C) there are a number of ways that project members should add safety to estimated lengths of activities.
D) there are a number of ways that project members should add buffer to the estimated length of activities.
Correct Answer:
Verified
Q20: Both positive and negative variations are usually
Q21: A(n)_ refers to a safety margin separating
Q22: In applying the principle of common cause
Q23: In classic project management,activity durations are estimated
Q24: Delays in project activity are known as
Q26: A(n)_ refers to a safety margin that
Q27: The _ Theorem states that if a
Q28: CCPM advocates modification of the project schedule
Q29: Project personnel often become involved in several
Q30: Keith welds a one-fourth-inch diameter ball bearing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents