All five members of a project team add 10% to their individual serial activities as a safety margin and submit their time estimates to the project manager.The manager adds the activity length estimates together and adds 10% for his personal safety margin.Then,anticipating a cut by top management,he adds another 20% to his final project estimate.Much to his surprise,top management cuts only 10% off his time estimate.How much of a cushion is now built into the project?
A) 25%
B) 31%
C) 56%
D) 88%
Correct Answer:
Verified
Q36: The first step in TOC methodology is
Q37: CCPM advocates putting off non-critical activities as
Q38: The _ syndrome describes the tendency to
Q39: In applying the principle of common cause
Q40: XYZ project organization has one workstation that
Q42: If a project activity experiences positive variation:
A)the
Q43: All five members of a project team
Q44: All five members of a project team
Q45: The student syndrome of wasting extra safety
Q46: The Central Limit Theorem says that if
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents