Which statement about critical chain project management is best?
A) CCPM is a complete solution to current project management scheduling needs.
B) In a multi-project environment where resources are shared,it is impossible to avoid multitasking.
C) There is substantial large-scale empirical research that confirms the efficacy of CCPM.
D) Lack of milestones within CCPM make coordination with external suppliers and subcontractors much easier.
Correct Answer:
Verified
Q44: What is the difference between the critical
Q93: A system-wide constraint is called a:
A)rope.
B)resource.
C)drum.
D)chain.
Q94: Use the project information in the table
Q95: A resource constraint can be exploited using
Q96: A project is represented by the activity
Q97: Use the project information in the table
Q99: A project is represented by the activity
Q100: A project is represented by the activity
Q102: What is the student syndrome and what
Q103: What are the recommendations for applying the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents