Activities A and B have a finish to finish relationship and early start and finish times as shown.What is the result of incorporating a 4-day lag between activities C and B?
A) The early finish for A increases to 31.
B) The early start time for A increases to 24.
C) The early finish time for B increases to 31.
D) The early start time for D falls to 23.
Correct Answer:
Verified
Q18: A(n)_ relationship is appropriate where two or
Q21: Each individual bar on a Gantt chart
Q23: The three principal methods for accelerating project
Q24: In analyzing crash options for project activities,each
Q25: The most common type of logical sequencing
Q26: Brook's Law states that the typical crashing
Q26: An activity of duration zero whose sole
Q27: Use the Gantt chart and the activity
Q65: AOA is a more useful technique than
Q92: Dummy activities are used in AOA networks
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents