An activity performed by a subcontractor is scheduled for 20 weeks at an anticipated cost of $100,000.Due to slippage on the critical path you need to reduce this activity by three weeks.If the subcontractor informs you that the activity can be completed in 15 weeks for $200,000,what is the slope for the activity?
A) $20,000 per week
B) $33,333 per week
C) $5,000 per week
D) $13,333 per week
Correct Answer:
Verified
Q43: Use the Gantt chart and activity list
Q44: One reason for crashing a project is:
A)the
Q45: Use the Gantt chart and activity list
Q46: Use the Gantt chart and the activity
Q47: Use the Gantt chart and activity list
Q49: A basic Gantt chart:
A)clearly displays early and
Q50: Use the Gantt chart and activity list
Q51: Given the cost information in the table,what
Q52: The process of accelerating a project is
Q53: Use the Gantt chart and activity list
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents