A complex project that is managed using a top-down,bottom-up approach to network diagrams means that:
A) management's top-down portion of the network contains the greatest detail.
B) top management does not have a basis for understanding the actual development of the project.
C) the top tier summary network does not give top management the basis for understanding the actual development of the project.
D) the bottom level information cannot be understood by those performing the actual work.
Correct Answer:
Verified
Q6: Sketch a network and use it as
Q56: What is project crashing and what are
Q85: Research has shown that,in general:
A)there is a
Q86: AON networks have an advantage over AOA
Q87: An AOA network:
A)cannot show a merge activity.
B)cannot
Q88: Networks would not be well suited for:
A)planning
Q89: What is the duration of the project
Q91: What is the cost to finish this
Q94: Consider the project described by the table
Q95: What is the minimum completion cost of
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents