Solved

Carbon Corporation Had a $2,000,000 Contract to Build a Small

Question 33

Multiple Choice

Carbon Corporation had a $2,000,000 contract to build a small hospital with total costs estimated at $1,600,000.It received the following payments and incurred the following expenses over the three-year contract period:
 Year  Payments  Expenses 1$400,000$300,0002$1,200,000$900,0003$400,000$550,000\begin{array}{lll}\underline{\text { Year } }&\underline{ \text { Payments }}& \underline{\text { Expenses }}\\1 & \$ 400,000 & \$ 300,000 \\2 & \$ 1,200,000 & \$ 900,000 \\3 & \$ 400,000 & \$ 550,000\end{array}

Under the percentage-of-completion method, how much profit should Carbon recognize in year 2?


A) $400,000
B) $300,000
C) $225,000
D) $150,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents