Figure 5-14
Deluxe Design Company makes custom furniture.On December 1,there were two jobs in process,Job 683,with a cost of $14,200 and Job 684 with a cost of $23,500.Jobs 685,686,and 687 were started during the month of December.Data on costs added during the month are as follows:
Overhead is applied to production at the rate of 80% of direct labor cost.Job 685 was completed on December 17.Job 684 was completed on December 21 and the client was billed at cost plus 45%.All other jobs remained in process.
Refer to Figure 5-14.
Required:
A.)Determine the amount of overhead to apply to each job for the period.
B.)Calculate the cost of work-in-process at the end of the month.
C.)Calculate the cost of finished goods,assuming that finished goods inventory on December 1st was zero.
Correct Answer:
Verified
Q161: The following information was taken from the
Q162: You Decide
You are the senior cost accountant
Q163: Bower Company manufactures a product in a
Q164: Figure 5-14
Deluxe Design Company makes custom furniture.On
Q166: Figure 5-13.
During February,Alexander,Inc.,worked on two jobs with
Q167: Consider two costing systems,normal costing and actual
Q169: If actual overhead for the year is
Q170: There are two major types of companies:
Q171: Figure 5-13.
During February,Alexander,Inc.,worked on two jobs with
Q189: Brady Corporation has estimated overhead to be
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents