Which of the following is true regarding the internal rate of return for a project?
A) If the internal rate of return is less than the required rate of return,the project will be rejected.
B) If the internal rate of return is equal to the required rate of return,the net present value of the project is zero.
C) If the internal rate of return is more than the required rate of return,the project will be accepted.
D) Managers may believe (in most cases,incorrectly) that the internal rate of return is the compounded rate of return earned by the initial investment.
E) all of these
Correct Answer:
Verified
Q100: The required rate of return used in
Q101: Shoring Company is considering a project with
Q104: The interest rate that sets the present
Q106: Jones Company is considering the purchase of
Q107: A firm is evaluating a project that
Q108: Jerry Hall invested in a project that
Q109: Jackson Company invests in a new piece
Q110: Figure 14-6. Present value of $1
Q123: The internal rate of return is defined
Q129: A firm is considering a project requiring
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents