Briggs Company Briggs Company Uses a Job-Order Costing System

Question 134

Multiple Choice

Briggs Company Briggs Company uses a job-order costing system.At the beginning of January,the company had two jobs in process with the following costs:
Briggs Company Briggs Company uses a job-order costing system.At the beginning of January,the company had two jobs in process with the following costs:   Briggs pays its workers $8.50 per hour and applies overhead on a direct labor hour basis. Refer to Briggs Company.During January,Briggs' employees worked on Job #649.At the end of the month,$714 of overhead had been applied to this job.Total Work in Process at the end of the month was $6,800 and all other jobs had a total cost of $3,981.What amount of direct material is included in Job #649? A) $ 677.00 B) $1,391.00 C) $2,142.00 D) $4,658.00 Briggs pays its workers $8.50 per hour and applies overhead on a direct labor hour basis.
Refer to Briggs Company.During January,Briggs' employees worked on Job #649.At the end of the month,$714 of overhead had been applied to this job.Total Work in Process at the end of the month was $6,800 and all other jobs had a total cost of $3,981.What amount of direct material is included in Job #649?


A) $ 677.00
B) $1,391.00
C) $2,142.00
D) $4,658.00

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents