The company is using a lot size of 700 units per order.Calculate the safety stock required for a cycle service level of 97.5%.In addition, what is the cost difference between the current policy and using the EOQ lot size? (safety stock/cost)
The expected annual demand is 123,670 units.The standard deviation for a week is 345 units.The ordering cost is $200 and the carrying cost is $3.00 per unit per year.In addition, the lead time is 3 weeks and there are 52 weeks per year.
A) 1171 units/$24,202
B) 8306 units/$36,384
C) 1171 units/$24,202.
D) 4060 units/$12,182.
Correct Answer:
Verified
Q11: By incorporating the demand uncertainty into EOQ
Q12: Explain is a paragraph how Economic Order
Q13: Choose the incorrect choice regarding the descriptions
Q14: ABC Classification uses dollar usage to classify
Q15: Choose the following assumptions that cannot be
Q17: One type of inventory control system periodically
Q18: Which of the following statements regarding inventory
Q19: In one sentence, define what demand is
Q20: Calculate the EOQ size for the following
Q21: Given the demand probability table, complete
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents