Classic Cleaning Company Classic Cleaning Company manufactures a cleaning solvent.The company employs both skilled and unskilled workers.To produce one 55-gallon drum of solvent requires Materials A and B as well as skilled labor and unskilled labor.The standard and actual material and labor information is presented below:
Standard:
Material A: 30.25 gallons @ $1.25 per gallon
Material B: 24.75 gallons @ $2.00 per gallon
Skilled Labor: 4 hours @ $12 per hour
Unskilled Labor: 2 hours @ $ 7 per hour
Actual:
Material A: 10,716 gallons purchased and used @ $1.50 per gallon
Material B: 17,484 gallons purchased and used @ $1.90 per gallon
Skilled labor hours: 1,950 @ $11.90 per hour
Unskilled labor hours: 1,300 @ $7.15 per hour
During the current month Classic Cleaning Company manufactured 500 55-gallon drums.
Round all answers to the nearest whole dollar.
Refer to Classic Cleaning Company.What is the total material mix variance?
A) $3,596 F
B) $3,596 U
C) $4,864 F
D) $4,864 U
Correct Answer:
Verified
Q178: Ponca City Company uses a standard
Q179: Genesis Company Genesis Company uses a
Q180: One unit requires 2 direct labor hours
Q181: Provide the correct term for each of
Q182: Classic Cleaning Company Classic Cleaning Company manufactures
Q186: National Toy Company National Toy Company has
Q187: National Toy Company National Toy Company has
Q188: Classic Cleaning Company Classic Cleaning Company manufactures
Q195: Define the following terms: standard cost system,total
Q196: List and discuss briefly the three standards
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents