Assume That Four Jobs,A-D,are in the READY Queue at Time

Question 34

Multiple Choice

Assume that four jobs,A-D,are in the READY queue at Time 0 and require the CPU cycles listed below.Using the SJN algorithm,the ____ job is run first. Job: A B C D
CPU cycle: 5 2 6 4


A) A
B) B
C) C
D) D