Brooksold Corporation Contracts to Have Zealent Construction Company Build a Factory

Question 90

Essay

Brooksold Corporation contracts to have Zealent Construction Company build a factory for $4,000,000.Days before the start of construction,Zealent withdraws from the contract.Brooksold invites proposals for the construction and contracts with Sierra Nos Builders for $3,800,000.Can Brooksold hold Zealent liable for nonperformance? What can the company recover as compensation for damages?

Correct Answer:

verifed

Verified

If the builder breaches a construction c...