The ES of an activity that has only one predecessor is simply the EF of that predecessor.
Correct Answer:
Verified
Q54: The critical path can be determined by
Q55: The _ is a project management technique
Q56: The main difference between PERT and CPM
Q57: Every network has at most one critical
Q58: What is the basic difference between PERT
Q60: A simple CPM network has three activities,
Q61: Explain why the critical path is the
Q62: The critical path for the network activities
Q63: The network below represents a project being
Q64: The network below represents a project being