Which of the following statements regarding PERT times is true?
A) The optimistic time estimate is an estimate of the minimum time an activity will require.
B) The optimistic time estimate is an estimate of the maximum time an activity will require.
C) The probable time estimate is calculated as t = (a + 4m + b) .
D) Pessimistic time estimate is an estimate of the minimum time an activity will require.
E) Most likely time estimate is an estimate of the maximum time an activity will require.
Correct Answer:
Verified
Q42: The critical path for the network
Q43: The Beta distribution is used in project
Q44: A simple CPM network has three activities,
Q45: Which of the following statements regarding CPM
Q47: Activity R on a CPM network has
Q49: A project being analyzed by PERT has
Q51: A simple CPM network has five activities,
Q53: Activity D on a CPM network has
Q82: The expected activity time in PERT analysis
Q100: Which of the following statements regarding PERT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents