The Beta distribution is used in project management to
A) calculate slack on activities not on the critical path
B) calculate the probability that a project will be completed within its budget
C) calculate pessimistic and optimistic activity times
D) determine which activity should be crashed
E) none of the above
Correct Answer:
Verified
Q33: A combination of effective Gantt chart use
Q42: The critical path for the network
Q44: A simple CPM network has three activities,
Q45: Which of the following statements regarding CPM
Q46: Which of the following statements regarding PERT
Q47: Activity R on a CPM network has
Q51: Which of the following statements regarding critical
Q82: The expected activity time in PERT analysis
Q100: Which of the following statements regarding PERT
Q109: A project manager is interested in crashing
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents