In a PERT network, non-critical activities that have little slack need to be monitored closely:
A) because PERT treats all activities as equally important.
B) because near-critical paths could become critical paths with small delays in these activities.
C) because slack is undesirable and needs to be eliminated.
D) because they are causing the entire project to be delayed.
E) because they have a high risk of not being completed.
Correct Answer:
Verified
Q85: A contractor's project being analyzed by PERT
Q86: Which of the following statements regarding PERT
Q87: A project being analyzed by PERT has
Q88: An activity on a PERT network has
Q89: The _ distribution is used by PERT
Q91: The bell curve is often appropriate for
Q92: The beta distribution is used in project
Q93: Variation in activities that are not on
Q94: A local project being analyzed by PERT
Q95: Which of the following statements regarding PERT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents