The network below represents a project being analyzed by Critical Path Methods. Activity durations are A = 5, B = 2, C = 12, D = 3, E = 5, F = 1, G = 7, H = 2, I = 10, and J = 6. a. What task must be on the critical path, regardless of activity durations?
b. What is the duration of path A-B-E-H-J?
c. What is the critical path of this network?
d. What is the length of the critical path?
e. What is slack time at activity H?
f. What is the Late Finish of activity H?
g. If activity C were delayed by two time units, what would happen to the project duration?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q35: What is a project organization?
Q48: Identify, in order, the six steps basic
Q58: What is the basic difference between PERT
Q66: What are the earliest activity start time
Q74: What is the objective of critical path
Q89: What are some of the ethical issues
Q92: Define slack.
Q104: Briefly describe the concept of cost/time trade-off
Q114: Describe in words how to calculate a
Q119: What are the advantages of using PERT
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents