The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the throughput time (makespan) to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:
a. Chart the progress of these five jobs through the two centres on the basis of the arbitrary order
A→B→C→D→E.
b. After how many hours will all jobs be completed?
c. Use Johnson's rule to sequence these five jobs for minimum total duration. Show your work in
determining the job sequence.
d. The optimal sequence is ________.
e. Chart the progress of the five jobs in this optimal sequence.
f. After how many hours will all jobs be completed?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q132: Use Johnson's rule to determine the
Q133: Complete the table, find average lateness,
Q134: Use Johnson's rule to determine the
Q135: A firm that specializes in desktop
Q136: At Morgan's Transformer Rebuilding, a set
Q138: The following jobs are waiting to
Q139: Lockport Marine Services, Inc. wishes to
Q140: The emergency room at a hospital
Q141: The following jobs are waiting to
Q142: Find the sequence for the priority
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents