The president of a consulting firm wants to minimize the total number of hours it will take to complete four projects for a new client. Accordingly, she has estimated the time it should take for each of her top consultants-Charlie, Gerald, Johnny, and Rick-to complete any of the four projects, as follows:
Project Hours
a. In how many different ways can she assign these consultants to these projects?
b. What is the total number of hours required by the following arbitrary assignment?
Charlie-B; Gerald-A; Johnny-D; Rick-C
c. What is the optimal assignment of consultants to projects? (Use the assignment method; SHOW YOUR WORK!)
d. For the optimal schedule, what is the total number of hours it will take these consultants to complete these projects?
e. What is the significance, if any, of the fact that Gerald is the best performer at all four projects?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q27: Explain, in your own words, how backward
Q108: A practitioner of family medicine begins her
Q115: What are some limitations of rule-based scheduling
Q121: Jack's Refrigeration Repair is under contract
Q123: Identify some scheduling optimization systems that are
Q123: A manufacturer has the following jobs
Q124: Bob Dresser operates a major appliance
Q125: At Morgan's Transformer Rebuilding, five jobs
Q126: There are 5 jobs (A, B, C,
Q127: Given the following chart of jobs assigned
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents