A brake system installer in an auto factory has an actual average time of 16.7 minutes on her task. The performance rating of the worker timed was estimated at 90%. Practice in this department is to allow 16% for the constant allowances. There is currently no variable allowance.
a. Find the normal time for the operation.
b. Compute the standard time for the operation.
c. Recompute the standard time if a variable allowance of 13% is factored in.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q173: A brake system installer in an auto
Q186: The data in the following table
Q188: A brake system installer in an auto
Q188: Suppose that an analyst takes 50 samples
Q189: A manufacturing plant assembly line job has
Q190: The data in the following table
Q192: A task involves positioning two metal
Q194: A time study of a certain service
Q195: A work sampling study requires an acceptable
Q196: A work sampling study requires an acceptable
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents