Gibson Products produces cast bronze valves for use in offshore oil platforms. Currently, Gibson produces 1600 valves per day. The 20 workers at Gibson work from 7 a.m. until 4 p.m., with 30 minutes off for lunch and a 15 minute break during the morning work session and another at the afternoon work session. Gibson is in a competitive industry, and needs to increase productivity to stay competitive. They feel that a 20% increase is needed.
Gibson's management believes that the 20% increase will not be possible without a change in working conditions, so they change work hours. The new schedule calls on workers to work from 7:30 a.m. until 4:30 p.m., during which workers can take one hour off at any time of their choosing. Obviously, the number of paid hours is the same as before, but production increases, perhaps because workers are given a bit more control over their workday. After this change, valve production increased to 1800 units per day.
a. Calculate labour productivity for the initial situation.
b. Calculate labour productivity for the hypothetical 20% increase.
c. What is the productivity after the change in work rules?
d. Write a short paragraph analyzing these results.
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q64: Operations managers should be well versed in
Q104: As the administrative manager in a law
Q110: Felicien grows mirlitons (that's Cajun for Chayote
Q111: Identify the three productivity variables used in
Q121: A firm cleans chemical tank cars in
Q122: The Dulac Box plant produces wooden packing
Q123: Mark's Ceramics spent $4000 on a
Q125: A local university is considering changes to
Q126: A swimming pool company has 100,000 labour
Q127: An industrial plant needs to make 100,000
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents