The concept of allocating extra time to a schedule for planning,problem solving,and maintenance is known as
A) preventative scheduling.
B) preventive maintenance.
C) over capacity maintenance.
D) under capacity scheduling.
Correct Answer:
Verified
Q62: American workers implementing lean prefer
A)the slow pace
Q63: The most prevalent applications of lean include
Q64: Lean production is difficult to implement when
A)demand
Q65: Mixed-model sequencing
A)facilitates total productive maintenance.
B)supports uniform production
Q66: All of the following are benefits expected
Q68: The benefits of lean production include all
Q69: Which of the following is not a
Q70: Combining the practice of preventive maintenance with
Q71: Which of the following is not typically
Q72: A _ kanban is used to order
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents