The slack time for an activity can be computed as
A) latest start time (LS) - latest finish time (LF) .
B) earliest start time (ES) + earliest finish time (EF) .
C) latest start time (LS) - earliest start time (ES) .
D) latest finish time (LF) + earliest finish time (EF) .
Correct Answer:
Verified
Q67: A project consists of the following four
Q68: The _ probability distribution is typically used
Q69: A project consists of the following four
Q70: The following table of probabilistic time estimates
Q71: The estimated variance for an activity with
Q73: The estimated variance for an activity with
Q74: The estimated mean time for an activity
Q75: A project consists of the following activities:
Q76: A project consists of the following activities:
Q77: A project consists of the following activities:
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents