The estimated variance for an activity with a most likely time (m) equal to 11 days,the optimistic time (a) equal to 6 days,and the pessimistic time (b) equal to 18 days is
A) 2 days.
B) 4 days.
C) 6 days.
D) 11 days.
Correct Answer:
Verified
Q68: The _ probability distribution is typically used
Q69: A project consists of the following four
Q70: The following table of probabilistic time estimates
Q71: The estimated variance for an activity with
Q72: The slack time for an activity can
Q74: The estimated mean time for an activity
Q75: A project consists of the following activities:
Q76: A project consists of the following activities:
Q77: A project consists of the following activities:
Q78: The estimated mean time for an activity
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents