The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
Table 9.2
-Using Table 9.2,how much slack is associated with activity C?
A) 0 weeks.
B) 4.50 weeks.
C) 12.67 weeks.
D) 31.00 weeks.
Correct Answer:
Verified
Q44: In general,the latest finish time for an
Q55: For an activity-on-node (AON)network,
A)arrows represent activities and
Q61: The following table of probabilistic time estimates
Q62: The following table of probabilistic time estimates
Q63: A project consists of the following four
Q65: The following table of probabilistic time estimates
Q66: A project consists of the following four
Q67: A project consists of the following four
Q68: A project consists of the following four
Q69: Which of the following is the universal
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents