The Following Table of Probabilistic Time Estimates (In Weeks)and Activity

Question 75

Multiple Choice

The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project.    Table 9.2 -Using Table 9.2,the probability that the project will take longer than 33 weeks to complete is approximately A) 0.19. B) 0.32. C) 0.68. D) 0.81.
Table 9.2
-Using Table 9.2,the probability that the project will take longer than 33 weeks to complete is approximately


A) 0.19.
B) 0.32.
C) 0.68.
D) 0.81.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents