As part of its quality-improvement program,a company is conducting a time study for a particular job.The time study encompassed 10 job cycles,and the results include the following cumulative times and performance rating factors for each element: The standard time for this job using an allowance factor of 16% is
A) 1.809 minutes.
B) 2.098 minutes.
C) 1.530 minutes.
D) 2.233 minutes.
Correct Answer:
Verified
Q1: In a time study the standard time
Q6: How many cycles should be used in
Q7: Workers often do not like to be
Q8: The normal time to perform a job
Q9: As part of a time study,a particular
Q9: Advantages of using a predetermined motion time
Q10: As part of its quality-improvement program,a company
Q10: Work sampling tends to be more disruptive
Q17: Determining the length of time it takes
Q18: The normal times for basic,generic micro motions
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents