A Company Hopes to Achieve a Daily Output of 200

Question 68

Multiple Choice

A company hopes to achieve a daily output of 200 units during 6 hours of production time.Assuming there is no lost time during the 6 hours of production,the desired cycle time to achieve the targeted level of output is


A) 3.0 minutes
B) 1.8 minutes
C) 1.5 minutes
D) 0.03 minutes

Correct Answer: