Casey Construction abandoned its $23 million North County road project after spending $7 million.By this time,one progress payment of $5 million had been made.The county immediately contracted with Beachwood Corp.to take over and finish the project for $21 million.Expectation damages for Casey Construction would be
A) the difference between $16 and $21 million.
B) the difference between $21 and $23 million.
C) zero,since Casey did $2 million of work where no payment was received.
D) none; only consequential damages might apply.
E) the difference between $18 and $21 million.
Correct Answer:
Verified
Q29: Businesses employ the use of exemption clauses
Q30: Where the parties to a contract agree
Q31: In a contract of sale,where the seller
Q32: Generally speaking,to successfully seek an equitable remedy
Q33: Where the losses suffered by an innocent
Q35: When a breach of contract has occurred,the
Q36: In contract,the material time for measuring damages
Q37: The fact that a party enters into
Q38: Liability in contract
A)acts as an incentive to
Q39: Carlos,an antique dealer,contracted to buy an antique
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents