B.C.Metal Works agreed to purchase steel rod from Vancouver Smelters Ltd.Delivery was to take place on April 1.On March 24,Vancouver Smelters advised Metal Works that the steel rod could not be delivered because of production problems.Metal Works accepted the anticipatory breach of Vancouver Smelters and reserved their right to sue for damages.On April 1,Metal Works commenced looking for an alternate supply of steel rod and located a supply in Seattle,Washington.The rods could not be delivered for seven days,causing Metal Works to shut down their operations for three days.Metal Works sued Vancouver Smelters for breach of contract.What legal obligation did Metal Works have,and what remedy would they be entitled to?
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q99: What is anticipatory breach,and why is it
Q100: Canadian common law jurisdictions take a narrower
Q101: Peevyhouse v.Garland Coal & Mining Company is
Q102: A party to a contract has a
Q103: On April 10,Mel entered into a contract
Q104: Buildco Limited enters into a contract that
Q105: Alice Munroe entered into a contract with
Q107: Name two equitable remedies.Describe three ways in
Q108: Troy Feldmon agreed to purchase a house
Q109: Describe why the doctrine of substantial performance
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents