When Developing Risk Mitigation Plans,one Should

Question 30

Multiple Choice

When developing risk mitigation plans,one should:


A) Be sure to plan for every possible thing that could go wrong.
B) Have a single person develop all risk scenarios.
C) Always use buffers as the primary risk mitigation technique.
D) Select mitigation plans that give the highest level of prevention or protection at the lowest investment.

Correct Answer: