After identifying the relevant risks associated with an IT initiative,which of the following is not something that the project team should consider regarding each risk?
A) The financial impact of the risk scenario occurring.
B) The probability of the risk scenario occurring.
C) The potential benefits of the risk scenario occurring.
D) The cost of mitigating the risk.
Correct Answer:
Verified
Q21: Benefits of IT initiatives should be measured
Q22: If the implementation costs greatly exceed the
Q23: Which of the following would not help
Q24: Acquisition costs for an IT initiative include
Q25: Which of the following is not one
Q27: Which of the following is the order
Q28: When considering the sensitivity of estimates used
Q29: Which of the following risks considers the
Q30: IDC estimates that what percent of IT
Q31: In addition to technology,which of the following
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents