Mauricio estimates that the first module of the project could be completed in as few as 15 days or could take as many as 25 days,but most likely will require 20 days.What is the 20 day estimate called?
A) best-case estimate (B)
B) probable-case estimate (P)
C) worst-case estimate (W)
D) logistical estimate (L)
Correct Answer:
Verified
Q60: A _ represents the work that one
Q61: Briefly explain the tasks performed by a
Q62: _,a human resource issue,is a possible cause
Q63: When a project manager first recognizes that
Q64: Explain the difference between qualitative and quantitative
Q66: _ can involve a modeling process called
Q67: _,a free cloud-based project management tool,runs in
Q68: Explain the three legs of a project
Q69: A _ is a proactive effort to
Q70: A _ consists of horizontal bars,connected with
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents