Ultimate U-bolts (UU) paid $161,175 for direct labor this month,paying $1.50 cents less per hour than planned.Fifty-four thousand pounds of bolts were produced and direct labor was paid for 9,210 hours.Producing one pound takes ten minutes.Which is true?


A) The direct labor wage variance is $4,605 unfavorable
B) The direct labor wage variance is $4,605 favorable
C) The direct labor wage variance is $4,500 favorable
D) The total labor variance is $17,805 favorable