Sherry is concerned that a new app her team is developing might not meet the customer's timeline requirements.What can her team do to determine whether they can complete the project on time or if the app features will need to be scaled back?


A) Allocate resources to the app's development.
B) Submit a system proposal.
C) Develop a prototype.
D) Complete a feasibility study.