Solved

An Automatic Extension of Time from the Regular Filing Date

Question 32

Multiple Choice

An automatic extension of time from the regular filing date for an individual tax return may be received, without giving the IRS a reason, for


A) 2 months.
B) 6 months.
C) 3 months.
D) 4 months.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents