Onar Development stopped progress payments to its general contractor, Shape Construction. Upon the advice of their attorney, Shape decided to sue for rescission of the contract rather than collect damages for breach. Shape will most likely
A) file for bankruptcy.
B) get expectation damages.
C) get an injunction.
D) collect under quantum meruit.
E) ask for specific performance.
Correct Answer:
Verified
Q30: A liquidated damages clause is the same
Q31: Danny agreed to sell a large painting
Q32: The union's contract would not expire for
Q33: Chin Chang agreed to buy an antique
Q34: All of the following may bar someone
Q36: Damages in contract are intended to punish
Q38: The Lockheart Community has a restrictive covenant
Q39: How can the judgment creditor extract money
Q40: A person may recover damages even if
Q78: An injunction is available in a variety
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents