Lake Construction Company uses the completed-contract method for long-term construction contracts. The information for a specific contract as of January 1, 2011, is shown below.
$600,000 of cost was incurred during 2011 and on December 31, 2011, the estimated remaining cost to complete was still $800,000. The correct balance for the Construction in Progress at December 31, 2011 is
A) $600,000.
B) $700,000.
C) $1,200,000.
D) $1,300,000.
Correct Answer:
Verified
Q21: A company uses the percentage-of-completion method to
Q24: The following data relate to a construction
Q26: Brown Construction Company uses the percentage-of-completion method
Q27: In 2011, Aldous Corp. began construction work
Q29: Shepard Construction Company has consistently used the
Q30: Paral Company began operations on January 2,
Q31: The following data relate to a construction
Q32: Wedtec Enterprises, which began operations on January
Q33: On May 1, 2011, Green Construction Company
Q39: In accounting for a long-term construction contract
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents