Timing the work elements using the snap-back method requires:
A) the worker to perform each job element as quickly as possible.
B) a larger sample size than using the continuous method.
C) the use of two stopwatches.
D) a smaller sample size than using the continuous method.
Correct Answer:
Verified
Q10: The performance rating factor in a time
Q11: The process of creating labor standards based
Q12: A larger sample size is required when
Q13: Time studies are appropriate for setting time
Q14: The snap-back method of time study resets
Q16: A time study is the method most
Q17: The select time is the average observed
Q18: The standard time for a work element
Q19: The key to creating a work standard
Q20: A(n) _ is the time required for