Table 7.2
A manufacturer using a kanban system has had problems with high inventory levels of one of the component parts it makes. Daily demand for the part is 3000 units, average waiting time during production is 0.20 day, processing time is 0.10 day per container, and a container holds 150 pieces.
-Use the information in Table 7.2.How many kanban containers would be required if a 10 % efficiency factor is used?
A) 3 or less
B) 4 or 5
C) 5 or 6
D) 7 or more
Correct Answer:
Verified
Q7: _ is the philosophy that waste can
Q45: _ refers to the goal of having
Q59: For firms along the supply chain, two
Q60: The main focus of lean systems in
Q69: The _ method produces the item when
Q72: A(n) _ assembly line produces a mix
Q79: _ are operating systems that are designed
Q102: Table 7.1
A toy company uses a kanban
Q109: Table 7.3
A company uses a kanban system.
Q110: Table 7.2
A manufacturer using a kanban system
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents