Table 7.3
A company uses a kanban system. The daily demand for part A is 4000 units. The average waiting time for a container of parts is 0.2 day. The processing time for a container of part A is 0.8 day, and a container holds 300 units.
-Use the information in Table 7.3.How many kanban containers would be required if a 5 % efficiency factor is used?
A) 10 or less
B) 11 or 12
C) 13 or 14
D) 15 or more
Correct Answer:
Verified
Q52: Any deviation from the optimum process that
Q56: Although small lot sizes are beneficial to
Q64: The standardization of components, called part commonality
Q69: The _ method produces the item when
Q70: Suppliers accept responsibility for helping to meet
Q80: _ is a system where the supplier
Q84: When suppliers are encouraged to locate near
Q119: Table 7.3
A company uses a kanban system.
Q136: The _ method produces the item in
Q144: Describe five types of waste that often
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents